(Problems 1–6 use this cost schedule, with FC = 48.)
| Q | FC | VC |
|---|---|---|
| 0 | 48 | 0 |
| 1 | 48 | 20 |
| 2 | 48 | 34 |
| 3 | 48 | 46 |
| 4 | 48 | 62 |
| 5 | 48 | 88 |
| 6 | 48 | 128 |
A. Total and Marginal Cost
Problem 1. Compute total cost (TC) at Q = 0 through 6.
Show solution
TC = FC + VC: 48, 68, 82, 94, 110, 136, 176.
Problem 2. Compute marginal cost for Q = 1 through 6.
Show solution
MC = ΔTC: 20, 14, 12, 16, 26, 40.
B. Average Costs
Problem 3. At Q = 4, compute AFC, AVC, and ATC.
Show solution
AFC = 48/4 = 12.
AVC = 62/4 = 15.5.
ATC = 110/4 = 27.5 (= AFC + AVC = 12 + 15.5 ✓).
Problem 4. At what output is ATC minimized? (Compute ATC across the table.)
Show solution
ATC = TC/Q: Q1 = 68, Q2 = 41, Q3 = 31.33, Q4 = 27.5, Q5 = 27.2, Q6 = 29.33.
Minimum ATC is at Q = 5.
Problem 5. At what output is AVC minimized?
Show solution
AVC = VC/Q: Q1 = 20, Q2 = 17, Q3 = 15.33, Q4 = 15.5, Q5 = 17.6, Q6 = 21.33.
Minimum AVC is at Q = 3.
C. Cost-Curve Relationships
Problem 6. Why does the vertical gap between the ATC and AVC curves shrink as output rises?
Show solution
Because ATC − AVC = AFC, and AFC = FC/Q falls continuously as output rises (the fixed cost is spread over more units).
So the gap narrows toward zero but never disappears.
Problem 7. Marginal cost at Q = 5 is 26 and at Q = 6 is 40, while minimum ATC (27.2) occurs at Q = 5. Explain what this illustrates about MC and ATC.
Show solution
MC (26) is below ATC just as ATC bottoms out, then MC (40) jumps above ATC, so MC crosses ATC right around its minimum. When MC < ATC it pulls ATC down; when MC > ATC it pulls ATC up.
Problem 8. Distinguish economies of scale from diseconomies of scale.
Show solution
Economies of scale: long-run average cost falls as output rises (spreading fixed costs, specialization). Diseconomies of scale: long-run average cost rises as output grows too large (coordination and management problems).
More Practice — Cost Schedules
Problem 9. A firm has fixed cost $40 and the variable-cost schedule below. At Q = 2, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 16 |
| 2 | 28 |
| 3 | 38 |
| 4 | 56 |
| 5 | 78 |
| 6 | 106 |
Show solution
TC = 40 + 28 = 68.
AFC = 40/2 = $20;
AVC = 28/2 = $14;
ATC = 68/2 = $34;
MC of unit 2 = 28 − 16 = $12.
Problem 10. A firm has fixed cost $40 and the variable-cost schedule below. At Q = 2, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 20 |
| 2 | 38 |
| 3 | 52 |
| 4 | 74 |
| 5 | 104 |
| 6 | 140 |
Show solution
TC = 40 + 38 = 78.
AFC = 40/2 = $20;
AVC = 38/2 = $19;
ATC = 78/2 = $39;
MC of unit 2 = 38 − 20 = $18.
Problem 11. A firm has fixed cost $80 and the variable-cost schedule below. At Q = 5, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 16 |
| 2 | 28 |
| 3 | 38 |
| 4 | 56 |
| 5 | 78 |
| 6 | 106 |
Show solution
TC = 80 + 78 = 158.
AFC = 80/5 = $16;
AVC = 78/5 = $15.6;
ATC = 158/5 = $31.6;
MC of unit 5 = 78 − 56 = $22.
Problem 12. A firm has fixed cost $40 and the variable-cost schedule below. At Q = 5, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 20 |
| 2 | 36 |
| 3 | 48 |
| 4 | 68 |
| 5 | 92 |
| 6 | 124 |
Show solution
TC = 40 + 92 = 132.
AFC = 40/5 = $8;
AVC = 92/5 = $18.4;
ATC = 132/5 = $26.4;
MC of unit 5 = 92 − 68 = $24.
Problem 13. A firm has fixed cost $40 and the variable-cost schedule below. At Q = 5, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 20 |
| 2 | 36 |
| 3 | 48 |
| 4 | 68 |
| 5 | 94 |
| 6 | 124 |
Show solution
TC = 40 + 94 = 134.
AFC = 40/5 = $8;
AVC = 94/5 = $18.8;
ATC = 134/5 = $26.8;
MC of unit 5 = 94 − 68 = $26.
Problem 14. A firm has fixed cost $60 and the variable-cost schedule below. At Q = 2, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 24 |
| 2 | 46 |
| 3 | 64 |
| 4 | 90 |
| 5 | 124 |
| 6 | 164 |
Show solution
TC = 60 + 46 = 106.
AFC = 60/2 = $30;
AVC = 46/2 = $23;
ATC = 106/2 = $53;
MC of unit 2 = 46 − 24 = $22.
Problem 15. A firm has fixed cost $40 and the variable-cost schedule below. At Q = 5, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 24 |
| 2 | 46 |
| 3 | 64 |
| 4 | 88 |
| 5 | 118 |
| 6 | 152 |
Show solution
TC = 40 + 118 = 158.
AFC = 40/5 = $8;
AVC = 118/5 = $23.6;
ATC = 158/5 = $31.6;
MC of unit 5 = 118 − 88 = $30.
Problem 16. A firm has fixed cost $60 and the variable-cost schedule below. At Q = 2, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 20 |
| 2 | 36 |
| 3 | 50 |
| 4 | 68 |
| 5 | 90 |
| 6 | 118 |
Show solution
TC = 60 + 36 = 96.
AFC = 60/2 = $30;
AVC = 36/2 = $18;
ATC = 96/2 = $48;
MC of unit 2 = 36 − 20 = $16.
Problem 17. A firm has fixed cost $40 and the variable-cost schedule below. At Q = 2, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 16 |
| 2 | 30 |
| 3 | 40 |
| 4 | 58 |
| 5 | 82 |
| 6 | 110 |
Show solution
TC = 40 + 30 = 70.
AFC = 40/2 = $20;
AVC = 30/2 = $15;
ATC = 70/2 = $35;
MC of unit 2 = 30 − 16 = $14.
Problem 18. A firm has fixed cost $48 and the variable-cost schedule below. At Q = 4, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 24 |
| 2 | 44 |
| 3 | 62 |
| 4 | 84 |
| 5 | 114 |
| 6 | 152 |
Show solution
TC = 48 + 84 = 132.
AFC = 48/4 = $12;
AVC = 84/4 = $21;
ATC = 132/4 = $33;
MC of unit 4 = 84 − 62 = $22.
Problem 19. A firm has fixed cost $60 and the variable-cost schedule below. At Q = 3, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 20 |
| 2 | 38 |
| 3 | 52 |
| 4 | 74 |
| 5 | 102 |
| 6 | 138 |
Show solution
TC = 60 + 52 = 112.
AFC = 60/3 = $20;
AVC = 52/3 = $17.33;
ATC = 112/3 = $37.33;
MC of unit 3 = 52 − 38 = $14.
Problem 20. A firm has fixed cost $48 and the variable-cost schedule below. At Q = 4, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 20 |
| 2 | 38 |
| 3 | 54 |
| 4 | 74 |
| 5 | 102 |
| 6 | 134 |
Show solution
TC = 48 + 74 = 122.
AFC = 48/4 = $12;
AVC = 74/4 = $18.5;
ATC = 122/4 = $30.5;
MC of unit 4 = 74 − 54 = $20.
Problem 21. A firm has fixed cost $60 and the variable-cost schedule below. At Q = 3, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 16 |
| 2 | 28 |
| 3 | 36 |
| 4 | 50 |
| 5 | 68 |
| 6 | 90 |
Show solution
TC = 60 + 36 = 96.
AFC = 60/3 = $20;
AVC = 36/3 = $12;
ATC = 96/3 = $32;
MC of unit 3 = 36 − 28 = $8.
Problem 22. A firm has fixed cost $60 and the variable-cost schedule below. At Q = 3, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 20 |
| 2 | 36 |
| 3 | 50 |
| 4 | 70 |
| 5 | 94 |
| 6 | 124 |
Show solution
TC = 60 + 50 = 110.
AFC = 60/3 = $20;
AVC = 50/3 = $16.67;
ATC = 110/3 = $36.67;
MC of unit 3 = 50 − 36 = $14.
Problem 23. A firm has fixed cost $60 and the variable-cost schedule below. At Q = 5, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 20 |
| 2 | 36 |
| 3 | 48 |
| 4 | 64 |
| 5 | 88 |
| 6 | 120 |
Show solution
TC = 60 + 88 = 148.
AFC = 60/5 = $12;
AVC = 88/5 = $17.6;
ATC = 148/5 = $29.6;
MC of unit 5 = 88 − 64 = $24.
Problem 24. A firm has fixed cost $60 and the variable-cost schedule below. At Q = 3, compute AFC, AVC, ATC, and MC.
| Q | VC |
|---|---|
| 1 | 20 |
| 2 | 36 |
| 3 | 48 |
| 4 | 68 |
| 5 | 92 |
| 6 | 120 |
Show solution
TC = 60 + 48 = 108.
AFC = 60/3 = $20;
AVC = 48/3 = $16;
ATC = 108/3 = $36;
MC of unit 3 = 48 − 36 = $12.